SOCOTECO II respectfully informs the following SCHEDULED POWER INTERRUPTION on JULY 25, 2020 (SATURDAY) and JULY 26, 2020 (SUNDAY) affecting the following areas.
JULY 25, 2020 (Saturday)
09:00AM – 12:00NN
(3HRS)
Affected Areas:
Rajah Buayan, FVR Village, Maunlad Extension and MSU Compound.
Purpose:
Installation of Tapping Pole at MSU Compound.
JULY 25, 2020 (Saturday)
08:00AM – 011:00AM (3HRS)
Affected Areas:
Portion of Purok Masunurin, Brgy. San Isidro, GSC
Purpose:
Extension of line for Telecommunication project.
JULY 26, 2020 (Sunday)
08:00AM – 01:00PM
(5HR)
Affected Areas:
Purok 5, 6 and 7 of Brgy. Glamang, Polomolok, South Cotabato
Purpose:
Upgrading of line from single phase to three phase line.